If you're pulling a permit in Marina del Rey, the single most important fact — and the one nearly every architect, contractor, and property owner gets wrong on their first project — is this: Marina del Rey is not part of the City of Los Angeles. It is unincorporated territory governed directly by Los Angeles County, and that changes almost everything about how your project gets approved.
Walk into the wrong counter with the wrong forms and you'll lose weeks. Ocean Permits specializes in exactly this kind of jurisdictional complexity — the same expertise we bring to fire rebuild permitting in Pacific Palisades and Altadena applies directly to Marina del Rey's layered, county-run approval process. We're a women-owned permit expediting firm based in Los Angeles, and Marina del Rey is one of the jurisdictions where hiring someone who already knows the players saves the most time and money.
Most of the Westside — Santa Monica, Culver City, and the City of Los Angeles itself — issues permits through its own municipal building department. Marina del Rey doesn't have one, because Marina del Rey isn't a city. It's an unincorporated census-designated place inside LA County's jurisdiction, sitting in the 90292 ZIP code, surrounded by (but legally separate from) the City of Los Angeles neighborhoods of Venice, Del Rey, and Playa del Rey.
That single fact triggers three separate, overlapping layers of government review:
LA County Department of Public Works, Building and Safety Division (BSD)
BSD issues the actual building permit and enforces the building code in Marina del Rey — not the Los Angeles Department of Building and Safety (LADBS). This is the layer most out-of-town design teams miss entirely, since Marina del Rey sits inside the 90292 ZIP code surrounded by City of Los Angeles neighborhoods that do use LADBS.
LA County Department of Regional Planning (DRP)
DRP handles land use, zoning entitlements, and administers the certified Marina del Rey Local Coastal Program (LCP), which governs Coastal Development Permits for the area.
LA County Department of Beaches and Harbors (DBH) — Asset Management Division
DBH manages the marina itself. Almost all of the land in Marina del Rey is owned outright by the County and leased to private operators under long-term ground leases (typically 25 to 99 years). DBH also staffs the Marina del Rey Design Control Board (DCB), which reviews the architectural design of nearly any exterior work before it can move forward.
No other Westside submarket on our site stacks all three of these on top of each other. It's genuinely a different animal, and it's why our coastal development permit experience matters as much here as it does in Malibu.
Confirm Jurisdiction and Pull the Lease Parcel Information
Before anything else, confirm the parcel sits within unincorporated Marina del Rey rather than the adjacent City of Los Angeles portions of the 90292 ZIP code — the boundary is not intuitive on a map. If the site is on County-owned land, pull the ground lease, which frequently contains improvement approval clauses requiring the lessor (LA County, acting through Beaches and Harbors) to sign off on scope before a permit application can even be deemed complete.
Pre-Application Review with the Design Control Board (for Exterior Work)
Any exterior modification — new construction, renovation, repainting, re-landscaping, signage, or facade changes — requires conceptual review by the Marina del Rey Design Control Board before or alongside the Coastal Development Permit application. The DCB meets on a monthly cycle and evaluates a project against the county's design guidelines for massing, materials, waterfront character, and site planning. Projects that skip this step routinely get bounced back — this is the single most common delay we see on Marina del Rey jobs.
Coastal Development Permit Application (DRP)
Marina del Rey sits entirely within the California Coastal Zone. Under the California Coastal Act (Pub. Res. Code §30600 et seq.), any "development" requires a Coastal Development Permit (CDP) unless a specific exemption applies. Because the Marina del Rey Local Coastal Program has been certified by the California Coastal Commission, the CDP is processed locally by LA County's Department of Regional Planning rather than by the Coastal Commission directly, though certain project types remain appealable to the Commission after local approval.
Building Permit Submittal Through EPIC-LA
Once land use and design approvals are in hand (or running concurrently), the building permit is submitted through EPIC-LA, LA County Public Works' online plan check and permitting portal for unincorporated areas — a completely separate database and reviewer pool from LADBS's system. Plan check is performed against the California Building Code as locally adopted under LA County Code Title 26 (Building Code). Fees are calculated on a construction-valuation basis, assessed by a different fee schedule than the City of LA.
Structural, Fire, Health, and Utility Sign-Offs
Depending on scope, a project may also need review from LA County Fire Department (which serves the marina, not LA City Fire), LA County Public Health for food-service buildouts, and coordination with the marina's utility and dock infrastructure. Restaurant and bar buildouts add California ABC licensing on its own separate track.
Plan Check Corrections and Resubmittal
Corrections cycle back through EPIC-LA. Because Marina del Rey projects often carry the added DCB and CDP layers, a correction on the building permit side can also trigger a re-look at design or coastal conditions if the fix changes the exterior scope.
Permit Issuance and Inspections
Once plan check clears and fees are paid, LA County BSD issues the permit and inspections are scheduled through EPIC-LA, performed by county building inspectors assigned to the Marina del Rey / West Area district office rather than a city inspector.
Certificate of Occupancy / Final Sign-Off
Final inspection, any outstanding DCB conditions of approval, and lease-required close-out documentation (many ground leases require the lessee to certify completed work back to the County) round out the process before a space can legally open for business.
Restaurant and bar buildouts add California ABC licensing on its own separate track — see our liquor license permitting services.
The channel-front dining corridor along Fisherman's Village, the Villa Marina area, and the promenades near Burton Chace Park sees constant turnover. These combine tenant improvement permitting, County health approval for commercial kitchens, DCB review, and often liquor license work running in parallel. Because these buildings sit on County ground leases, landlord (lessee) approval and sometimes DBH Asset Management sign-off precede the permit application itself.
Much of Marina del Rey's residential stock — the towers along Admiralty Way, Bali Way, and Via Marina — sits on leasehold land. Unit renovations that touch structural elements, plumbing risers, or exterior balconies require both an HOA/leasehold approval process and a county building permit.
Boatyards, fuel docks, chandleries, yacht brokerages, and marine repair facilities occupy much of the working waterfront, carrying additional environmental and stormwater conditions tied to their proximity to the water.
Marina del Rey's hotel properties, most on long-term County leases, periodically undergo renovation cycles requiring the full stack: DCB design review, CDP, and county building permit.
Smaller commercial suites along Mindanao Way and Admiralty Way follow the same county process at a smaller scale — but the paperwork burden per square foot is often higher than a comparable project in the City of LA.
| Factor | Marina del Rey (Unincorporated LA County) | City of Los Angeles |
|---|---|---|
| Governing jurisdiction | Los Angeles County | City of Los Angeles |
| Building permit agency | LA County Public Works, Building & Safety Division (BSD) | LA Department of Building and Safety (LADBS) |
| Governing building code | LA County Code Title 26 | LA Municipal Code Ch. IX |
| Land use / zoning authority | LA County Dept. of Regional Planning (DRP) | LA City Planning Department |
| Online permit portal | EPIC-LA | LADBS online services / plan check portals |
| Design review | Marina del Rey Design Control Board (DCB) — required for most exterior work | Design review only where a specific overlay/HPOZ applies |
| Coastal Development Permit | Required for most development; issued by County DRP under the certified Marina del Rey LCP | Required in Coastal Zone areas; issued by LA City Planning |
| Land ownership | Predominantly County-owned, ground leases (25–99 yrs) | Predominantly fee-simple private ownership |
| Fire/emergency services | LA County Fire Department | LA Fire Department (LAFD) |
| Typical added review layer | DCB conceptual review + lessor/ground-lease approval | HPOZ or overlay-zone review where applicable |
Because of the added layers, Marina del Rey projects generally take longer to reach permit issuance than a comparable scope filed with LADBS — DCB conceptual review runs on a monthly meeting cycle and CDP review adds its own comment/noticing period. A straightforward interior TI with no exterior changes can sometimes skip DCB and move closer to standard commercial plan check timelines. See our post on how long permits take in Los Angeles.
Permit fees in Marina del Rey are calculated under LA County's valuation-based fee schedule tied to Title 26, a different fee table than LADBS uses. On top of building permit fees, budget for DRP's coastal permit processing fee, any DCB submittal fee, and — because most parcels are leasehold — potential lessor review or improvement-approval costs baked into the ground lease itself. See our permit expediter cost guide, and a consulting session with our team can pressure-test your specific project's fee exposure before you file.
Because the County owns most of the underlying land in Marina del Rey, permitting here is never purely a government-to-applicant transaction — it's also a landlord relationship, with the County of Los Angeles as landlord. Ground leases commonly include improvement clauses requiring lessor review of any capital work above a certain dollar threshold, insurance and bonding requirements tied to construction activity on County property, and reversion language that makes lenders and title companies pay close attention to how improvements are permitted and documented. A contractor who treats a Marina del Rey buildout like any other LA tenant improvement can find the job stopped cold by a lease compliance issue that has nothing to do with the building code at all.
Because nearly every parcel in Marina del Rey sits within a few hundred feet of navigable water, projects here routinely trigger environmental review that a similarly sized inland project would never see. Construction and demolition activity near the channel is subject to stormwater pollution prevention requirements, and any work that touches a dock, bulkhead, seawall, or slip-adjacent structure typically requires coordination with the Department of Beaches and Harbors' harbor operations staff. Grading or land alteration close to the shoreline can also independently trigger Coastal Development Permit review even when the building scope itself is minor.
Ocean Permits is a women-owned permit expediting firm built around exactly this kind of jurisdictional complexity. We built our reputation navigating LA's most demanding rebuild environments — including the fire-recovery permitting surge in Pacific Palisades and Altadena. We handle the full range of Marina del Rey work — restaurant and bar permitting along the waterfront, tenant improvements in leasehold retail and office space, liquor license coordination, and pre-project consulting. We offer a free consultation to review your specific parcel, lease status, and scope before you file anything.
Call 213-277-8777 to talk through your Marina del Rey project, or contact us to get started.
No. Marina del Rey is an unincorporated community within Los Angeles County. It has its own ZIP code (90292) and is surrounded by, but legally separate from, the City of Los Angeles. Building and zoning authority rests with the County, not LA City government.
The Los Angeles County Department of Public Works, Building and Safety Division (BSD), issues building permits through the county's EPIC-LA online portal — not the Los Angeles Department of Building and Safety (LADBS), which only has jurisdiction inside the City of LA.
Almost certainly, if your project involves new construction, exterior alteration, change of use, or grading. Marina del Rey sits within the California Coastal Zone, and under the California Coastal Act (Pub. Res. Code §30600 et seq.), most development requires a CDP, processed by LA County's Department of Regional Planning under the certified Marina del Rey LCP.
The DCB is a county review body that reviews the architectural design and site planning of nearly any exterior work in Marina del Rey. If your project changes anything visible from outside the building, plan on DCB conceptual review before or alongside your CDP application.
Most of Marina del Rey's land is owned by Los Angeles County and developed by private operators under long-term ground leases, typically 25 to 99 years. This affects nearly every project because the ground lease often requires lessor approval for capital improvements in addition to standard government permits.
It varies by scope, but projects involving exterior work typically take longer because of the added Design Control Board and Coastal Development Permit review layers, both running on their own review cycles.
LA County Code Title 26 (Building Code), which adopts the California Building Code with county-specific amendments — a separate code adoption from the Los Angeles Municipal Code.
No. Marina del Rey permits go through EPIC-LA, LA County Public Works' portal for unincorporated areas, a separate system from any City of Los Angeles portal.
Typically yes — County health department review for the commercial kitchen, Design Control Board review for signage or facade changes, a Coastal Development Permit for most exterior scope, and if alcohol is served, a separate California ABC licensing process.
The Los Angeles County Fire Department, not the Los Angeles Fire Department (LAFD), which covers only incorporated City of LA territory.
Yes. HOA or leasehold association approval and a Los Angeles County building permit are two entirely separate requirements.
Line-item government fees follow a different valuation-based schedule under Title 26, and projects with exterior scope carry additional CDP and DCB submittal costs. Professional expediting fees are generally comparable to other complex-jurisdiction LA projects.